Went to the site to check on the outstanding issues with the pre-plaster inspection and was surprised that they have started plastering the walls. My initial reaction was, oh no, they hurriedly put the plaster on so that I won't be able to check if they fixed the issues. Well, they still have not fixed some of them but the critical ones (like the missing wall batts) they already did.
First off.. the facade taking shape.
Side bricks almost done
View from the entrance
Bricking still not done at the back of the house
These wall sarking got ripped and I had to fix them myself